Why Concrete Cracks Between the Joints: Spacing, Depth and Timing in Eastern Idaho

Covered concrete patio with a scored joint pattern poured by Skinner Customs in Eastern Idaho

Written by

in

Concrete control joints are the most misunderstood thing on a flatwork job. People look at the lines in a driveway and think they are decoration, or a seam where two pours met. They are neither. They are pre-planned cracks, cut or tooled where I want the concrete to break so it does not break somewhere I did not choose.

I run Skinner Customs out of Rigby and I pour flatwork from Rexburg down to Shelley. When somebody calls me in March upset about a crack, the first thing I do is look at where the joints are. Most of the time the crack is not a mystery. The panels were too big, the joints were too shallow, the layout had a corner in it that was never going to survive, or the saw came out too late. That is a workmanship problem, not bad luck.

Here is how joints are supposed to work, what the industry actually recommends, and what our freeze-thaw winters do to a slab that was jointed wrong.

Concrete is going to move, so the question is where

Concrete shrinks as it cures and keeps moving with moisture and temperature for its whole life. It is strong in compression and weak in tension, so when that shrinkage gets restrained by the base, by a footing, by a wall, the tension builds until something gives.

The National Ready Mixed Concrete Association puts it plainly in CIP 6, Joints in Concrete Slabs on Grade: “Joints are simply pre-planned cracks.” That is the whole idea. Nobody in this trade can promise you a slab with zero cracks. What a contractor can do is decide in advance where the cracking goes, make those locations straight, and make them easy to seal and maintain.

In Eastern Idaho that matters more than it does in a mild climate. A slab in Jefferson or Bonneville County goes through freeze and thaw cycles every late fall and every spring, sometimes several in one week. Water finds a crack, freezes, expands and widens it. A straight tooled joint sheds that water. A random crack with a lip on it holds it and spalls at the edges.

Joint spacing: the number that actually matters

The spacing rule is the one thing I wish every homeowner knew before they collect bids.

CIP 6 says: “The maximum joint spacing should be 24 to 36 times the thickness of the slab. For example, the joint spacing for a 4-inch thick slab should be about 10 feet.” It then adds a hard ceiling: “It is further recommended that joint spacing be limited to a maximum of 15 feet.”

Run that against the slabs people actually have:

Slab thickness Recommended joint spacing Practical layout
4 inch about 8 to 10 feet residential driveways, sidewalks, patios
5 inch about 10 to 12 feet heavier driveways, RV parking
6 inch about 12 to 15 feet shop and pole barn slabs, truck traffic

A standard two-car driveway is roughly 20 by 20. On 4 inches that is four panels, not one big field with a joint down the middle. I see 12 and 14 foot panels in 4-inch residential work around here constantly, and those slabs crack through the middle of the panel within a couple of winters. Nothing was wrong with the concrete. There was just too much of it between relief points.

Panel shape is the other half of it

Spacing alone does not save a slab if the panels are the wrong shape. CIP 6: “All panels should be square or nearly so. The length should not exceed 1.5 times the width. Avoid L-shaped panels.”

Long skinny panels crack across the middle. L-shaped panels crack at the inside corner, every time, because that corner concentrates the tension. If your driveway wraps around toward a side door or widens out for a parking pad, that corner needs a joint running through it so the geometry is broken into squares and rectangles. When I lay out a job with a dogleg in it, the joint plan is the first thing I sketch, before anybody sets a form board.

The same goes for anything sticking up out of the slab. A porch post, a column, a light pole base. The slab has to be isolated from it or the slab will crack at it.

Depth and timing: where joints get cheated

A joint only works if it goes deep enough to create a weakened plane. CIP 6 again: “For contraction joints, the joint groove should have a minimum depth of one quarter the thickness of the slab, but not less than 1 inch.”

On a 4-inch slab that is 1 inch minimum. A decorative scoreline a quarter inch deep is not a control joint. It looks like one, and I have torn out plenty of slabs where the surface had pretty lines on it and the real crack ran right beside one of them because the groove never reached down into the slab.

Timing is the other place corners get cut. There are three legitimate ways to do it, and CIP 6 gives the windows:

  • Tooled joints, run early in the finishing process and rerun later so the groove does not bond back together. This is what I use on most residential flatwork.
  • Early-entry dry-cut joints, “generally run 1 to 4 hours after completion of finishing,” and at least 1 inch deep.
  • Conventional saw-cut joints, which “should be run within 4 to 12 hours after the concrete has been finished.”

That 4 to 12 hour window is real, and in our climate it moves. A hot August pour in Idaho Falls sets fast and wants the saw early. A 40-degree October pour in Rigby is still green the next morning. If sawing is delayed too long, the slab cracks on its own schedule before anybody shows up with a blade. If it is too early, the edges ravel. A contractor who pours at 2 p.m. and goes home without a plan for the joints that night is gambling with your slab.

What joints do not fix

Joints control shrinkage cracking. They do nothing about a slab that moves because the ground under it moved.

If the base was not compacted, if the fill was dumped in one lift instead of several, if a trench crossing under the slab was backfilled loose, the slab will settle and crack regardless of a perfect joint layout. That is why my joint plan is the last 10 percent of the job and the base prep is the first 50 percent. Minimum 4 inches of compacted gravel, placed in lifts on questionable soils, before any steel goes down.

Steel does not prevent cracks either. I use rebar, number three or number four on an 18-inch grid, and it earns its keep by holding a cracked slab together and keeping the two sides level with each other. Wire mesh does not do that job. CIP 6 is blunt about mesh: “Note that wire mesh will not prevent cracking. Mesh tends to keep the cracks and joints from opening up.” Mesh also gets walked flat during the pour and ends up at the bottom of the slab doing nothing. If a bid comes in under my eight dollar a square foot floor, mesh instead of rebar is one of the usual reasons.

What to ask before you sign

Three questions, and you will learn more than an hour of reading reviews.

  1. What is my joint layout? A contractor who knows the trade can tell you where the lines will fall and why, before the pour. If the answer is “we will figure it out when we get there,” that is your answer.
  2. How deep, and tooled or sawed? You are listening for one quarter of the slab thickness, and a specific plan for when the joints happen relative to finishing.
  3. How are you isolating the slab from the house, the garage slab and the sidewalk? Driveways, patios and walks need to move independently from footings, walls and each other. Premolded filler at those edges, not a bonded butt joint.

Frequently asked questions

Are control joints the same as expansion joints?

No. Control or contraction joints are grooves cut into one slab to control where it cracks. Isolation or expansion joints separate a slab from something else, a wall, a footing, a garage slab, a sidewalk, so the two can move independently. Most residential jobs need both.

How far apart should joints be on a 4-inch driveway?

About 8 to 10 feet, following the 24 to 36 times thickness rule, and never more than 15 feet. On a typical 20-foot wide driveway that means panels, not halves.

My slab cracked right next to a joint. Why?

Usually the joint was too shallow to create a real weakened plane, so the concrete found its own path a few inches away. Decorative scorelines get blamed for this a lot. A groove under an inch deep on a 4-inch slab is not doing structural work.

Can joints be added to an existing slab?

They can be saw-cut after the fact, and sometimes that helps a slab that is still sound but under-jointed. It will not undo cracks that already formed, and it is not a fix for settling. Have somebody look at the slab before spending money on cuts.

Do I need to seal the joints?

On exterior flatwork here, yes, and it is cheap insurance. Open joints collect water, snowmelt and de-icing salt, and that is exactly the recipe for freeze-thaw damage at the joint edges. Cleaning and resealing joints is one of the few maintenance items on concrete that actually pays off.

Get the joint plan before the concrete shows up

If you are getting bids for flatwork in Rigby, Idaho Falls, Rexburg, Ammon or Shelley, ask every bidder where the joints go. The honest ones will have an answer and it will sound a lot like the numbers in this post, because those numbers are not mine, they are the industry’s.

Need concrete work in Eastern Idaho? Call Zach at Skinner Customs at (208) 390-5794 or start at skinner-customs.com.


Content produced in partnership with S4 Media, marketing partner of SwagerBuilds LLC.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *